#TonyS
1 messages · Page 1 of 1 (latest)
I can give you the req_id req_SUwhCyHzmN9B1m and the schedule id sub_sched_1MsmiODhXwH3fVpP0H8SoyGX
Thanks. So what's not working for you?
As you would see the end date we specified is 1707692400
which is 11 feb 2024
And the schedule says that the subscription will last until 3 of may
That's the first phase. The second phase will be until 2024
The first phase should last 1 month and the second until 11 feb 2024
Here I can see that the second phase will last until 3 may 2024 and not 11 feb 2024
Sorry if I'm unclear
No I think you are clear. Still need to check in to your schedule but the server is pretty busy. I will pull in a colleague who can help
Have you tested this with a test clock to see if the phases would actually work properly a year out? It is possible that this is a dashboard UI thing rather than what the schedule will actually do https://stripe.com/docs/billing/testing/test-clocks