#Compact 20Kg/s Sour Gas Boiler

16 messages ยท Page 1 of 1 (latest)

leaden pelican
#

Currently struggling on getting enough chill into the SG at the condensing area for it to liquify at >4Kg/s

#

So I either need to increase heat extanger effeciency, which I don't know how to do, or get more chill out of the SC, which I don't know how to do

#

Ideally both

leaden pelican
#

Did this and set the AT's to -250. Surprisingly doesn't make solid methane. Heat extanger is bringing SG to -105c. Which leaves about 900KDTU brute force cooling needed, my two AT's can just supply half of that, provided the heat extanger does not loose any efficiency when upping the flow it should possibly function as is

leaden pelican
#

Scrap that. It can do all of this for 10Kg/s assuming no heat loses. Not 20.

leaden pelican
#

My SG-NG heat extanger does 3c difference per segment at the top and 40c towards the bottom. Any ways to even this out? And would that make it more effecient?

leaden pelican
#

Current iteration. Functional for 15Kg/s now upping it to 20

#

Oh shit.

leaden pelican
#

I'm 300kDTU's short from this functioning. Once again the heat extanger needs to be improved, which is thermium, or I need to add another AT

#

Added gas/liquid pipes and conveyors, sorted it out.

leaden pelican
#

Final Design, tested at 5x speed. Fully functional, Petrol input, roughly 110Kw output.

#

Time to do an 80Kg/s version ๐Ÿ˜†๐Ÿ˜ญ

leaden pelican
#

1 Slight modification because I didn't realise SC in pipes was reaching absolute zero, the design still works with original SS's.